DEACTIVATION OF PACK FLOW CONTRO VALVE

Pack Flow control Valve 23HB

DEACTIVATION:-

Open the Air conditioning panel of Pack1/Pack2

(1)Remove and discard the LOCK WIRE from the Pressure seal cap (Brass colour in pic) 

(2)Remove the Pr seal cap from the Pack flow control unit

(3)Make sure that the Forked valve position indicator is in the CLOSED position.refer in the picture.

(4)Install the Pr.Cap seal between the forks of the forked-Valve position lever and threaded boss

(5) Safety the pr seal cap with lock wire.

As soon as this cap is opened,air moves out and FCV butterfly goes to Close position.

Check that Fork is now at a close position.

Follow step 4 and 5 as above.

For more details refer relevant AMM.